Alex is Sprintlaw’s co-founder and principal lawyer. Alex previously worked at a top-tier firm as a lawyer specialising in technology and media contracts, and founded a digital agency which he sold in 2015.
Priya has signed a lease for a small ramen bar in Manchester. The contractor says the fit out will take eight weeks, the kitchen supplier needs measurements next week, and the landlord wants drawings before anyone touches the ventilation.
It all feels exciting until Priya realises the quote is only two pages long. It says very little about delays, variations, defects, approvals or what happens if the builder leaves before the restaurant is ready to open.
If you're fitting out a restaurant, cafe or bar, your fit out agreement is one of the most useful documents you'll sign. A good one doesn't just record the price. It gives you a practical plan for getting from empty shell to opening night with fewer surprises.
- Do You Need A Fit Out Agreement For A Restaurant?
- What Should Be Included In A Restaurant Fit Out Contract?
- How Should Milestones And Payments Work?
- What Happens If The Contractor Wants To Change The Price Or Scope?
- Who Handles Permits, Landlord Approval And Compliance?
- What Should Handover Look Like Before Opening?
- Key Takeaways
Do You Need A Fit Out Agreement For A Restaurant?
Yes, you should have a written fit out agreement before work starts, especially for hospitality premises where timing, compliance and handover all affect your opening date.
A restaurant fit out usually involves more than cosmetic works. You might be installing commercial kitchen equipment, extraction, grease management, fire safety systems, plumbing, electrics, flooring, signage and seating. Those works often need to line up with your lease, landlord approvals, building control and your premises licence position.
Without a written agreement, you may struggle to prove what the contractor promised, what was included in the price and whether the work is late or defective. A short quote can help, but it usually won't deal with the parts that cause disputes.
Your agreement should clearly cover:
- Scope: exactly what the contractor is responsible for, including drawings, materials, equipment installation and coordination with other trades and sub-contractors.
- Price: the contract sum, provisional sums, excluded items and how VAT is treated.
- Timing: start date, milestones, practical completion and what happens if there are delays.
- Approvals: landlord consent, building control, planning, fire safety and licensing issues.
- Changes: how variations are requested, priced and approved.
- Defects: what must be fixed, when and what you can hold back until it's done.
- Handover: certificates, manuals, warranties, keys, as-built drawings and final sign-off.
For larger or more technical works, a standard commercial fit out contract may be better than a simple contractor quote. What you need depends on the value and risk of the project, so it's worth getting the document tailored before you sign.
What Should Be Included In A Restaurant Fit Out Contract?
A restaurant fit out contract should set out what will be built, when it will be finished, how payment works and who is responsible for approvals, risks and defects.
Here is a practical outline you can use when preparing your instructions. This isn't a finished legal document, and a lawyer should tailor it before you use it, but it will help you spot what might be missing.
- Parties And Premises: name your business, the contractor and the exact site address, including any unit number or shopping centre details.
- Scope Of Works: attach drawings, specifications, schedules, finishes, equipment lists and any exclusions.
- Programme: include the start date, milestone dates, long lead items and the target practical completion date.
- Contract Price: state the fixed price or pricing method, VAT position, provisional sums and assumptions.
- Payment Milestones: link payments to real progress, not just calendar dates, and set out invoice requirements.
- Variations: require written approval before changes affect the price or programme.
- Delays: explain which delays extend time, what evidence is needed and whether delay damages apply.
- Permits And Approvals: allocate responsibility for landlord consent, building control, planning, utilities, fire safety and licensing impacts.
- Health And Safety: cover site safety, insurance and Construction (Design and Management) Regulations 2015 duties.
- Defects And Rectification: set the defects period, response times and your rights if defects aren't fixed.
- Handover: list the certificates, manuals, warranties, test results and documents required before final payment.
- Termination: explain when either side can end the agreement and what happens to payment, materials and site access.
Be careful with fit out contractor terms that are attached to a quote. They can be heavily weighted towards the contractor, for example by allowing broad price increases, short defect periods or payment before key stages are genuinely complete.
How Should Milestones And Payments Work?
Milestones should be tied to completed stages of work, because paying too much too early can leave you exposed if the project slows down or the contractor walks away.
For a restaurant fit out, a sensible payment structure might include:
- a modest deposit to secure the start date or order materials
- a payment when strip out and first fix works are complete
- a payment when kitchen services, ventilation and key infrastructure are installed
- a payment at practical completion
- a retention amount held until defects are fixed
For example, Priya agrees a 100,000 pound plus VAT fit out. Instead of paying 50,000 pounds upfront, she agrees:
- 10,000 pounds on signing
- 25,000 pounds after first fix plumbing and electrics are signed off
- 30,000 pounds after kitchen extraction, flooring and joinery are installed
- 25,000 pounds at practical completion
- 10,000 pounds retained until the end of a 12 week defects period
That structure gives the contractor cash flow, but it also gives Priya leverage if snagging items aren't finished. The right percentages will depend on your project, materials and bargaining position.
Many commercial fit out contracts are construction contracts under the Housing Grants, Construction and Regeneration Act 1996. That matters because there are statutory payment rules, including payment notices, pay less notices and the right to adjudicate disputes. Your agreement should sit comfortably with those rules, rather than ignore them.
You should also check whether materials paid for but not yet installed become yours, and whether they're insured while stored off site. This is especially relevant for expensive kitchen equipment, bespoke joinery and imported tiles or fittings.
What Happens If The Contractor Wants To Change The Price Or Scope?
Changes should only affect the price or deadline if they're approved through a clear written variation process.
Restaurant fit outs are full of moving parts. You might discover that the existing drainage isn't where the plans said it was, your landlord might require a different extraction route, or you might decide to upgrade the bar counter once you see the space taking shape.
The issue isn't that variations happen. The issue is uncontrolled variations, where everyone remembers the conversation differently.
Your agreement should say:
- who can request a variation
- what information the contractor must provide before the change is approved
- whether the change affects the contract price
- whether the change affects the completion date
- who signs off the change for your business
- what happens if urgent works are needed to protect the site or comply with safety requirements
A good variation clause might require the contractor to give you a written variation notice with the cost, timing impact and reason for the change. You then approve or reject it in writing before the work is done.
Try not to rely on informal site chats. A text or email trail is much better than a handshake, but a signed variation form is cleaner again.
Also watch for vague allowances in the quote. If an item is listed as a provisional sum, ask what it includes and what could push the final cost up. If the contractor says something is excluded, make sure you know who is doing it instead. Gaps between the builder's contract, kitchen supplier agreement, fire consultant's scope and landlord's contractor can get expensive very quickly.
Who Handles Permits, Landlord Approval And Compliance?
It depends on the type of approval, but your agreement should clearly allocate responsibility so nothing falls between you, the contractor and the landlord.
For a restaurant, the key approvals and compliance checks often include:
- Landlord consent: your lease may require consent for alterations, signage, services, extraction, shopfront changes or structural works. This is often documented in a licence to alter.
- Planning permission: you may need permission for external changes, extraction equipment, signage or a change of use. Listed buildings and conservation areas can add extra controls.
- Building control: building regulations may apply to ventilation, fire safety, drainage, accessibility, electrics, structure and other parts of the works.
- Premises licence: under the Licensing Act 2003, layout changes can affect your licensed plans. You may need to check whether a variation is required before trading alcohol from the new layout.
- Food safety: your kitchen layout should support safe food handling under food hygiene rules enforced by your local authority.
- Fire safety: under the Regulatory Reform (Fire Safety) Order 2005, the responsible person needs suitable fire risk arrangements for the premises.
- Health and safety: The Construction (Design and Management) Regulations 2015 apply to fit-out works in Great Britain. For a non-domestic project, if more than one contractor is involved, or it's reasonably foreseeable that more than one contractor will be involved, the client must appoint a principal designer and principal contractor in writing before the construction phase begins.
Your contractor might help with drawings, certificates and technical submissions, but that doesn't automatically mean they take full responsibility for legal approvals. Spell it out.
Before works start, ask for a responsibility matrix. This can be as simple as a list of approvals with one column for your business, one for the contractor and one for the landlord or consultant. If the landlord won't approve the works until certain documents are provided, build that into the programme so you don't lose weeks waiting for paperwork.
What If The Fit Out Is Delayed Or Defective?
If the fit out is delayed or defective, start by checking the contract, recording the issue and using the notice process before the dispute gets bigger.
Delays are especially painful for restaurants because rent, staff recruitment, stock planning and marketing may already be underway. If your contractor misses practical completion by three weeks, you may still be paying rent and utilities without being able to trade.
Your agreement should deal with delay in a practical way. It should say what counts as an excusable delay, such as late landlord approval, unexpected site conditions or changes you requested. It should also say when the contractor has to notify you and provide evidence.
You can also consider liquidated damages. This is a pre-agreed amount the contractor pays for each day or week of culpable delay. The amount should be commercially justifiable and not out of all proportion to the legitimate interest you're protecting. For example, if a two week delay could reasonably cost you 6,000 pounds in rent, staff training costs and wasted launch marketing, you might use that kind of calculation when setting the figure.
Defects need the same clarity. Your contract should define practical completion and include a snagging process, a defects period and response times for urgent issues.
What To Do First If Something Goes Wrong
- Check The Contract: look at the notice, defects, delay and payment clauses before reacting.
- Keep Records: save photos, site meeting notes, emails, invoices, delivery dockets and messages.
- Give Written Notice: explain the issue, refer to the contract and ask for a plan to fix it.
- Hold Back Only Where Allowed: if you plan to withhold payment, follow the contract and any construction payment rules carefully.
- Get Help Early: if opening is at risk or a large payment is disputed, get advice before positions harden.
Many disputes can be solved on site if the contract gives everyone a clear path. If it doesn't, you may end up arguing about process instead of fixing the restaurant.
What Should Handover Look Like Before Opening?
Handover should be more than getting the keys back. It should be a documented sign off that the premises are ready, compliant and safe for your team to operate.
For hospitality premises, missing handover documents can delay your opening or create problems later when you need to prove that systems were installed correctly.
Your handover checklist might include:
- practical completion certificate or signed completion record
- snagging list with deadlines for each item
- electrical installation certificates and test results
- gas safety documentation where relevant
- ventilation and extraction commissioning information
- fire alarm, emergency lighting and fire safety system records
- building control completion certificate or evidence of sign off where applicable
- warranties for equipment, joinery, appliances and materials
- operation and maintenance manuals
- as-built drawings, especially for services hidden behind walls or ceilings
- confirmation that landlord reinstatement or fit out requirements have been met
- keys, access codes and alarm details
Don't leave handover until the day before your launch party. Build it into the contract as a condition of final payment or release of retention.
This is also the point where your lease and fit out contract overlap. If your lease says you need to reinstate alterations at the end of the term, keep clear records of what was installed and approved. Future you'll be grateful when you're renewing the lease, selling the business or negotiating an exit.
For larger projects, you may also want a separate project manager, architect or contract administrator under a clear advisory agreement to certify stages and practical completion. That can add cost, but it may reduce the risk of paying for work that isn't finished or compliant.
Key Takeaways
- A restaurant fit out agreement should cover more than price. It should deal with scope, milestones, variations, approvals, defects, delays and handover.
- Link payments to real progress and consider retention so you have leverage if defects aren't fixed.
- Variations should be approved in writing before they change the price or completion date.
- Check landlord consent, building control, planning, licensing, fire safety and CDM responsibilities before works start.
- Handover should include certificates, warranties, manuals, as-built drawings and a clear snagging process.
- Templates and short quotes often miss hospitality specific risks, so it's worth tailoring the contract to your site and opening plan.