Selected cases

UK Supreme Court · [2024] UKSC 18

RTI Ltd v MUR Shipping BV

The UK Supreme Court held that a reasonable-endeavours obligation in a force majeure clause did not require a party to accept payment in a...

UK Supreme Court15 May 2024

Plain-English explainers, not legal advice. Use the linked official source for section-level detail, and get advice for your situation.

Get legal help

Start here

Quick read

  • A force majeure clause should say whether workarounds can include alternative payment, delivery or performance.
  • The UK Supreme Court held that a reasonable-endeavours obligation in a force majeure clause did not require a party to accept payment in a currency the contract did not...

Use this to check

  • Reasonable endeavours ordinarily aim to preserve contractual performance
  • Clear words are needed before a party gives up a valuable contractual right
  • Alternative currency and payment mechanics should be drafted expressly

Decision snapshot

  1. What happened

    • MUR Shipping agreed to carry bauxite for RTI under a contract requiring payment in US dollars.
    • When the United States sanctioned RTI's parent company, dollar payments were likely to be delayed.
    • MUR suspended shipments under the force majeure clause.
    • RTI offered to pay in euros and cover the conversion costs, but MUR refused because the contract gave it a right to dollars.
  2. What the court had to decide

    • Did the requirement to use reasonable endeavours to overcome the force majeure event oblige MUR to accept non-contractual performance that would have achieved a similar economic result?
  3. What the court decided

    • The Supreme Court unanimously allowed MUR's appeal.
    • Unless the contract clearly says otherwise, reasonable endeavours are directed at achieving performance according to the contract.
    • They do not require a party to surrender its right to the agreed performance or accept a different bargain.

Practical impact

Practical read

  • A force majeure clause should say whether workarounds can include alternative payment, delivery or performance.
  • Without clear wording, a reasonable-endeavours obligation is unlikely to force a business to accept something materially different from the bargain it signed.

Useful next steps

  • Reasonable endeavours ordinarily aim to preserve contractual performance
  • Clear words are needed before a party gives up a valuable contractual right
  • Alternative currency and payment mechanics should be drafted expressly
  • Force majeure notices should identify the event, causal effect and attempted mitigation
  • The event must fit the clause

The payment problem that stopped the shipments

MUR had agreed to carry monthly shipments of bauxite from Guinea to Ukraine. RTI had agreed to pay freight in US dollars. The contract included a force majeure clause and said the affected party had to use reasonable endeavours to overcome the event.

US sanctions were imposed on RTI's parent company in April 2018. The parties later agreed that banks were highly likely to delay RTI's dollar payments. MUR served a force majeure notice and suspended shipments.

Why the courts disagreed

Decision-makerResult
Arbitral tribunalMUR should have accepted euros because the workaround avoided the problem without detriment.
High CourtReasonable endeavours did not require acceptance of non-contractual payment.
Court of Appeal majorityRTI's offer overcame the event because it achieved the same result without detriment.
Supreme CourtMUR could insist on contractual performance and rely on force majeure.

The Supreme Court favoured a clear rule. Contractual performance means performance according to the agreed terms. A reasonable-endeavours proviso ordinarily asks what can be done to achieve that performance, not whether a different performance would be commercially acceptable.

What the decision protects

The judgment protects contractual certainty and the freedom not to accept a new bargain. A right to payment in a chosen currency can carry credit, banking, accounting and operational value beyond the immediate conversion cost.

The Court did not say that parties can ignore mitigation. MUR still had to show the force majeure event caused the failure and could not be avoided by reasonable steps that achieved the agreed performance.

What the court focused on

  • The event must fit the clause
  • The event must cause the failure or delay relied on
  • The affected party must take reasonable steps within the contractual bargain
  • A proposed substitute should be assessed against the exact clause wording

Draft the workaround before the disruption

  1. Define the event

    Cover the risks that matter to the deal, including sanctions, banking restrictions and supply interruption where appropriate.

  2. Define acceptable substitutes

    State whether alternative currency, delivery locations, suppliers or methods can satisfy the mitigation obligation.

  3. Allocate extra cost

    Say who pays conversion, transport, compliance and implementation costs for an approved workaround.

  4. Set the notice process

    Require prompt notice, evidence of impact, mitigation updates and a clear route back to ordinary performance.

Common questions

Does reasonable endeavours mean accepting any practical workaround?

No. In this case the obligation did not require MUR to accept payment in euros when the contract required US dollars. Different wording can produce a different result.

Can a force majeure clause require alternative performance?

Yes, if it says so clearly. Parties can define approved currencies, substitute delivery methods, change-control processes or temporary workarounds.

Is this only a shipping case?

No. The Court treated the issue as one of general importance to force majeure and reasonable-endeavours clauses in commercial contracts.

Related topics

How Sprintlaw can help

Update history

Case20 July 2026

Force majeure and post-employment restraint cases added

New explainers cover alternative performance under a force majeure clause and severance of an overbroad non-compete.