Selected cases

High Court of Justice · [2025] EWHC 2899 (Ch)

AJP Homes Limited v Tate Estates (Lambert House) Limited

AJP Homes Limited v Tate Estates (Lambert House) Limited [2025] EWHC 2899 (Ch) is a High Court appeal about neighbour access rights during...

High Court of Justice6 Nov 2025

Plain-English explainers, not legal advice. Use the linked official source for section-level detail, and get advice for your situation.

Get legal help

Start here

Quick read

  • The main lesson is to treat the transfer as an operating document, not just a title document.
  • AJP Homes Limited v Tate Estates (Lambert House) Limited [2025] EWHC 2899 (Ch) is a High Court appeal about neighbour access rights during a redevelopment.

Use this to check

  • A broad express right of way can include stopping to load and unload, depending on the wording and the physical setting.
  • A separate parking right does not automatically prevent the same area also forming part of the route if the deed supports that reading.
  • A covenant not to block the green land was an important part of how the court read the transfer as a whole.

Decision snapshot

  1. What happened

    • AJP Homes Ltd owned 106 Station Parade, Harrogate.
    • Tate Estates (Lambert House) Ltd owned the neighbouring property at 108 Station Parade.
    • The two sites were separated by a small alley.
    • Access arrangements between them were governed by a transfer dated 29 November 2016.
  2. What the court had to decide

    • The High Court had to decide a limited appeal from a County Court trespass dispute.
    • The first issue was whether Tate Estates had admitted legal responsibility for alleged trespasses committed by its contractor, Harris CM Ltd.
  3. What the court decided

    • The High Court dismissed AJP Homes’ appeal.
    • It upheld the County Court’s interpretation of the 2016 transfer and confirmed that the broad right of way over the green land, granted for all purposes connected with the property, was wide enough to include stopping to load and unload.
    • It also upheld the finding that the right of way allowed access to the undercroft parking area and extended over the pink-and-green area as well as the separate parking right.

Practical impact

Practical read

  • The main lesson is to treat the transfer as an operating document, not just a title document.
  • A broad right of way may allow more than simple movement from A to B.
  • On the wording and facts here, it included stopping to load and unload and practical access to the redeveloped building’s undercroft parking.
  • A separate parking right did not stop the same pink-and-green area also forming part of the route.

Useful next steps

  • A broad express right of way can include stopping to load and unload, depending on the wording and the physical setting.
  • A separate parking right does not automatically prevent the same area also forming part of the route if the deed supports that reading.
  • A covenant not to block the green land was an important part of how the court read the transfer as a whole.
  • Planning material does not automatically narrow private rights granted in a transfer unless the deed clearly says so.
  • Before works start, businesses should turn title wording into written site access rules for staff and contractors.

The story

This dispute grew out of a redevelopment next door to an existing residential property in Harrogate. AJP Homes owned 106 Station Parade. Tate Estates owned 108 Station Parade, a site that had previously been Lambert House and was later redeveloped into an apartment block.

The sites were separated by a small alley. Access over part of AJP’s land was governed by a 2016 transfer. That transfer became the centre of the case because it granted both a right of way over land shaded green and a separate parking right over an area edged pink.

During the build, Tate Estates’ contractor, Harris CM Ltd, used the access land for construction activity. AJP said this went too far and amounted to trespass. Tate Estates said the transfer rights were broad enough to cover what happened on site.

Practical sense check

  • Neighbouring land was needed for practical site access
  • The transfer granted both a right of way and a separate parking right
  • The dispute arose during demolition and redevelopment activity
  • One side alleged trespass and the other alleged interference with access rights
  • The case turned on the wording of the 2016 transfer and the attached plan

How the dispute reached the High Court

The original claim was heard in the County Court in Leeds. AJP sought damages for 31 alleged acts of trespass between July and October 2021. It said the contractor had stopped vehicles, unloaded materials and stored items on AJP’s land beyond the rights granted by the transfer.

Tate Estates accepted only four acts of trespass and said they were de minimis. It also argued that the transfer allowed stopping and unloading on the green land. On top of that, Tate Estates counterclaimed, saying AJP had erected Heras fencing that interfered with its right of way and parking easement.

The County Court dismissed AJP’s trespass claim and awarded Tate Estates nominal damages on the counterclaim for interference with its right of way. The judge also made declarations recording key findings and ordered AJP to pay 90% of Tate Estates’ costs of the claim, with a payment on account of £160,000, while ordering Tate Estates to pay the costs of the counterclaim.

AJP then appealed. Permission to appeal was granted on limited grounds only. The High Court appeal therefore was not a full rehearing of every issue in the case. It focused on the contractor responsibility point and specific questions about how the transfer should be interpreted.

What the court focused on

  • County Court claim for trespass by AJP Homes
  • Counterclaim by Tate Estates for interference with right of way and parking easement
  • County Court dismissed the trespass claim
  • County Court awarded nominal damages on the counterclaim
  • High Court appeal was limited to contractor responsibility and construction of the transfer

What the court had to decide

The appeal raised two main groups of issues. The first was whether Tate Estates had admitted legal responsibility for the acts of its contractor, Harris CM. The second, and more important, was how the 2016 transfer should be interpreted.

On construction, the court had to decide whether the right of way over the green land allowed vehicles not only to pass but also to stop and load or unload. It also had to decide whether the alley could be used to reach the undercroft parking area in the redeveloped building, and whether the right of way extended over the pink-and-green area as well as the separate parking right.

These were not abstract title questions. They went directly to whether the complained-of site activity was within the granted rights or was actionable trespass. They also affected the counterclaim, because if Tate Estates had broader rights than AJP accepted, fencing off part of the route could itself be wrongful interference.

Practical sense check

  • Was Tate Estates legally responsible for the contractor’s alleged trespasses?
  • Did the right of way include stopping on the green land?
  • Did it include loading and unloading there?
  • Did it allow access through the alley to the undercroft parking area?
  • Did the route also extend over the pink-and-green area?

What the transfer actually said

The wording of the transfer did most of the work in this case. Clause 2.1 granted an exclusive right to park one domestic vehicle or small van within the area edged pink on Plan 2, and or for such other use as authorised by planning, subject to maintaining that area.

Clause 2.2 granted a right of way over the area shaded green on Plan 2, with or without vehicles, for all purposes connected with the property. That is broad language. The court treated it as important that the right was not expressed in narrow terms.

Clause 2.3 also formed part of the background. It gave rights to construct a road and landscaping on the green land, install service media and carry out related works, subject to conditions including producing necessary consents, carrying out works properly, causing as little disturbance as reasonably practicable and making good damage.

Clause 4.1 mattered as well. The buyer covenanted not to block, or allow others to block, the area shown shaded green on Plan 2 with vehicles or otherwise, other than as permitted by clause 2.1. That covenant helped the court read the right of way and the parking right together.

Key points

  • A broad right of way over the green land
  • The right applied with or without vehicles
  • The right was for all purposes connected with the property
  • A separate express parking right existed over the pink area
  • There was also an express covenant not to block the green land except as permitted

What the High Court decided

The High Court dismissed the appeal. It upheld the County Court’s interpretation of the 2016 transfer and left the main result in place. In practical terms, that meant AJP’s trespass case failed on the key points that mattered.

On the right of way, the court agreed that the wording was broad enough to include stopping on the green land for the purpose of loading and unloading. The judge accepted that a right to pass can, depending on the wording and physical setting, include stopping to load and unload.

The court also agreed that the right of way allowed access through the alley to the undercroft parking area. It rejected the argument that the transfer should be read as limited by planning material in a way the deed did not clearly say.

Finally, the court upheld the view that the right of way extended over the pink-and-green area as well as the separate parking right. The deed was read as a whole, including the covenant not to block the green land.

The contractor point

AJP also argued that Tate Estates had effectively admitted responsibility for the acts of Harris CM, its contractor. The High Court did not allow the appeal on that ground.

The important practical point is not that contractor responsibility can never matter. It plainly can. The point here was narrower. The High Court said that even if AJP had been right about the admission issue, that would not have changed the justice of the result on the facts found below.

The judge noted that most of the alleged trespasses found below were insignificant apart from a cabin and a skip for a two month period and the storage of flooring and walling stone for a number of days. AJP had not pursued injunctive relief at trial, and there was no basis for remitting liability for a retrial given the limited damages position identified in the judgment.

The court also noted that, even on AJP’s own best case, any negotiating damages would have been very limited on the findings that were not separately appealed. That is why this part of the judgment should be read carefully. It does not remove contractor risk in general. It says that, on these facts, the point would not have changed the overall result.

Practical sense check

  • Do not overread this part of the case
  • The court did not say contractor conduct is irrelevant
  • It said the point would not have changed the result on these facts
  • The main commercial lesson still comes from the transfer wording
  • Liability arguments are weaker if the underlying access rights are broad enough

Why the wording mattered so much

The court gave real weight to the actual words used in the transfer. A right to pass with or without vehicles over the green land for all purposes connected with the property is not naturally read as a bare right to move through without ever stopping.

The background also supported that reading. At the time of the 2016 transfer, it was known that Lambert House was due for demolition. The court considered that the parties could not sensibly have intended access rights so narrow that demolition and redevelopment could not practically be carried out.

The physical layout mattered too. The route led to Lambert House and into the alley. The court accepted that stopping to load and unload on the green land was part of practical access in that setting. It also noted that the original building extended right up to the boundary, making it difficult to see how demolition could have begun without vehicles stopping on the green land.

The High Court also stressed that the trial judge had carefully analysed the transfer against the admissible background and then tested the result against ordinary principles of contractual interpretation. That mattered on appeal because AJP was largely challenging the weight given to background facts, which is usually difficult to overturn where the lower court has taken a careful and lawful approach.

The pink-and-green area

One of the more practical points in the case was whether the area that carried the separate parking right could also form part of the route. AJP argued that the pink-and-green area should be treated only as a parking area, or at least that any right of way there was limited to access for parking.

The High Court upheld the County Court’s broader reading. The right of way extended over that area as well as the separate parking right. The court treated clause 4.1 as important because it showed the parties contemplated that the green land should not be blocked except as permitted by the parking clause. That only made sense if the area still had a wider access function.

The court also accepted that the seller was not effectively excluded from all sensible use of the area. The judgment records that the parties contemplated some continuing use of the land, including amenity or landscaping use, and that conflicts between the rights should be resolved sensibly rather than by assuming the most extreme possible use.

Practical sense check

  • Read route rights and parking rights together, not in isolation
  • Check whether the same land is both coloured for access and edged for parking
  • Look for a covenant dealing with blocking or obstruction
  • Do not assume a parking right makes the area unavailable for all other route use
  • Think about how the rights work on the ground, especially at tight corners

Planning documents did not rewrite the deed

One of AJP’s arguments was that planning material should narrow the transfer rights, especially in relation to access to the undercroft. The High Court rejected that argument on the wording before it.

That is a useful point for businesses. Planning permission and private property rights are different things. Planning documents may be relevant background, but they do not automatically cut down clear rights granted in a transfer unless the deed itself clearly links the rights to those documents or to a specific approved scheme.

That distinction matters in practice. A planning consultant may say a layout is acceptable from a planning perspective, but that does not answer whether deliveries, turning movements or access over neighbouring land are privately authorised. You need both pieces to line up.

Documents to keep in order

  • Check whether the transfer expressly refers to planning documents
  • Check whether rights are tied to a specific approved plan
  • Do not assume a site plan narrows rights unless the wording says so
  • Review planning permission and title rights separately
  • Recheck access rights if the design changes during the project

How businesses should read this case

If you are buying or developing a site, this case is a reminder that easements and covenants can shape build logistics just as much as the construction contract. A broad right of way may support deliveries, turning, stopping and access to new parking areas if the wording and context point that way.

If you own the burdened land, the case is a warning against assuming that inconvenient site activity is automatically trespass. Before fencing off land, restricting access or threatening proceedings, check the transfer and plans carefully. A wrong move can trigger a counterclaim for interfering with rights of way or parking easements.

If you are instructing contractors, do not leave these issues buried in title documents. Turn them into written site rules. The legal wording should be reflected in delivery instructions, traffic management, neighbour communications and escalation procedures.

This is especially important on constrained urban sites. Tight corners, shared alleys and mixed route and parking areas create room for genuine disagreement. A short legal review before works start is usually far cheaper than arguing later about trespass, delay and who pays the costs.

Documents and conduct to check before works start

Sense check

  • Read the transfer and every plan attached to it
  • Check the exact wording of any right of way
  • Check whether there is a separate parking right and how it interacts with the route
  • Look for covenants not to block, obstruct or interfere with access land
  • Check whether rights are granted to the owner only or also to those authorised by it
  • Review whether contractors, delivery drivers and occupiers are within the intended scope of use
  • Check whether any temporary storage on the land is clearly authorised
  • Compare the title wording with the actual site layout and turning space
  • Review planning documents, but do not assume they override the deed
  • Issue written access instructions to the site team and contractors

For many businesses, the practical failure is not in the drafting but in the handover from legal documents to site operations. If the deed allows stopping to unload, say so clearly. If it does not allow storage, say that too. If a route must stay clear except for a defined use, make that part of the contractor brief.

It is also worth keeping a simple record of any neighbour discussions and temporary arrangements. If a dispute later arises, contemporaneous instructions, plans and emails can help show whether the site team acted within the granted rights or drifted beyond them.

Dates and status

The High Court judgment was handed down on 6 November 2025 by Mr Justice Leech in the Business and Property Courts in Leeds. It concerned an appeal from a County Court judgment dated 27 March 2024. Permission to appeal had been granted on 29 November 2024, limited to specific grounds. The High Court dismissed the appeal.

The hearing took place on 10 October 2025. The order under appeal had been made on 1 May 2024 and recorded the County Court’s declarations, dismissal of the trespass claim, nominal damages on the counterclaim and the main costs orders.

Common questions

What was this case about in simple terms?

It was a neighbour access dispute during a redevelopment. One owner said the developer and its contractor had trespassed by stopping vehicles, unloading materials and using an alley and parking area beyond what the transfer allowed. The developer said the transfer gave it broad rights of way and parking rights. The High Court agreed with the developer and dismissed the appeal.

Did the High Court say a right of way can include stopping and unloading?

Yes, on the wording and facts of this case. The transfer granted a right to pass with or without vehicles over the green land for all purposes connected with the property. The court held that this was broad enough to include stopping to load and unload on the green land.

Did the separate parking right limit the route?

Not here. The court upheld the view that the right of way extended over the pink-and-green area as well as the separate parking right. The deed had to be read as a whole, including the covenant not to block the green land except as permitted.

Was this just about planning permission?

No. The court treated planning material as potentially relevant background, but it did not accept that planning documents cut down the transfer rights in a way the deed itself did not clearly express. Private property rights and planning permission are different issues.

What should a business do before starting works that rely on neighbour access?

Review the transfer, plans and covenants carefully. Check whether the wording allows stopping, loading, unloading, turning, access to new parking areas and use by contractors. Then turn that legal position into written site instructions so the project team and contractors know what is and is not allowed.

Related topics

How Sprintlaw can help