This dispute came out of a land sale for a holiday park development at the former North Selby Mine site near York. The Bowl area of the site had been marketed for static caravans, and outline planning permission allowed static caravans there subject to a limit on pitch numbers.
During due diligence, Westfield’s solicitor discovered that two former mineshafts in the Bowl were surrounded by a Zone of Influence. The Coal Authority guidance described that zone as a mathematical buffer around a mine entry. Westfield was told there was a 27 metre radius around each shaft.
That created a commercial problem. Westfield’s solicitor warned that a large part of the Bowl might be undevelopable for the intended caravan use. The original £3 million bid was then reduced, and the parties agreed a lower upfront price of £2.6 million with a deferred consideration clause worth up to £400,000 if the affected land was later released in the right way.
The negotiations matter because they show how the payment mechanism was shaped. One side first proposed a broad idea based on the area proving developable, with a partial-use option linked to caravan pitches. The parties then moved to a square metre formula. In the signed agreement, the trigger was tied to written confirmation that the Zone of Influence was reduced, and the value was fixed at £88.96 per square metre.
The contract also contained a separate use restriction. Westfield agreed not to locate caravans, erect temporary or permanent buildings, or park vehicles within the Zone of Influence. That meant the same defined term sat at the centre of both the payment clause and the operational restriction.
Later, the Coal Authority said there was no objection to static caravans being sited provided they did not infringe the shaft caps, while permanent structures still should not be built within the wider calculated zone. Harworth said that was enough to trigger the extra payment. Westfield said it was not the event the contract described.