Fixed Fee Subcontractor Agreements In Construction

byAlex Solo8 min read

Mike runs a small carpentry business in Manchester. He agrees to complete the second-fix carpentry on a townhouse project for a fixed fee of GBP 14,000, thinking the drawings are final and the site will be ready on Monday.

By Wednesday, the builder has asked for extra shelving, changed two door specifications, and told Mike the plastering delay means he can't start half the rooms yet. Suddenly, that fixed fee doesn't feel fixed at all.

Fixed price construction work can be great for cash flow and certainty, but only if your subcontractor agreement is clear about the scope, payment timing, delays, defects, insurance and variations. Otherwise, the argument usually becomes: was that included, or is it extra?

What Is A Fixed Fee Subcontractor Agreement?

A fixed fee subcontractor agreement is a contract where you agree to complete a defined package of work for a set price, instead of charging by the hour or day.

In construction, that might cover work such as electrical installation, plumbing, plastering, joinery, tiling, roofing, decorating, groundwork, supply and install works or fit-out works. The contractor usually engages the subcontractor to deliver a specific part of the main project.

The key word is defined. A fixed fee doesn't mean you have to absorb every change, delay or extra request. It means the price is fixed for the scope described in the agreement.

A good fixed fee subcontract should answer questions like:

  • What exact work is included in the price?
  • What drawings, specifications and site information are you relying on?
  • What isn't included?
  • When do you get paid, and what happens if payment is late?
  • How are variations approved and priced?
  • Who is responsible for site access if the site isn't ready?
  • What happens if defects are found after completion?

For many construction contracts in England and Wales, the Housing Grants, Construction and Regeneration Act 1996, often called the Construction Act, also affects payment notices, suspension rights and adjudication. If your agreement doesn't deal with these properly, terms from the Scheme for Construction Contracts may be implied.

Do You Need A Written Agreement For Fixed Price Construction Work?

Yes, you should use a written agreement for fixed price construction work because it gives both sides a clear record of the scope, price and risk allocation.

Verbal agreements can still be legally binding, but they're hard to prove. If the job changes, the site is delayed or payment is withheld, you may be left trying to piece together emails, WhatsApp messages, drawings and site conversations.

A written subcontract is especially useful when:

  • The works are worth more than a small call-out job
  • You're relying on drawings, specifications or a programme
  • The project has staged payments or retention
  • You're working under a main contractor who has obligations to an end client
  • You need to show insurance, health and safety or compliance documents
  • You're supplying both labour and materials, or using labour hire

If you're the contractor, your agreement helps you manage your subcontractor and protect your obligations under the main contract. If you're the subcontractor, it helps you avoid being asked to deliver extra work for the same fixed fee.

Free templates can be a useful starting point, but construction contracts are very fact-specific. A template may miss practical issues like site readiness, retention, pay less notices, defects periods, design responsibility, site access limitations and variation approval. It's usually worth having the document tailored before you rely on it.

What Should Your Scope Of Works Say?

Your scope of works should say exactly what you're doing, what you aren't doing, and what assumptions your fixed price is based on.

This is the part of the agreement that does the heavy lifting. If the scope is vague, the fixed fee becomes a guessing game. Phrases like "all carpentry works" or "complete electrical package" can sound simple, but they often create problems because different people read them differently.

A clear scope should identify the relevant drawings, specification documents, schedules, revisions and any site information you used to price the job. If your price assumes a particular product, finish, quantity, access arrangement or working hour, say so.

It can also help to include a short list of exclusions. For example, you might exclude making good works by others, out of hours work, waste removal, temporary protection, design work, additional fixings, unforeseen ground conditions or works caused by changes to other trades. The point isn't to be difficult. It's to make sure everyone prices, programs and manages the project on the same basis.

If you're taking on design responsibility, the agreement should say what that responsibility covers. There's a big difference between installing to someone else's drawings and designing a compliant system yourself. The fixed fee should match the role you're actually taking on.

How Should Variations Be Handled?

Variations are one of the biggest pressure points in fixed fee subcontracting. A client or main contractor may say, "it's only a small change", but several small changes can quickly wipe out your margin.

Your agreement should set out a simple process for variations. Usually, this means the contractor must request or approve the variation in writing before the subcontractor starts the changed work. The writing doesn't need to be complicated, but it should record what is changing, the price impact and any effect on the programme.

Common variation triggers include changed drawings, extra quantities, different materials, altered sequencing, site instructions, acceleration, delays caused by others, and work required because an area wasn't ready when promised.

The agreement should also say how variations are valued. Options include agreed fixed prices, schedule of rates, daywork rates, cost plus a margin, or another pricing method. If you don't deal with this upfront, you may end up arguing about whether the extra work was included, whether it was authorised, and what it was worth.

As a practical rule, don't rely only on a site conversation. Follow up in writing before you start, even if it's a short email confirming the instruction and the extra cost. That paper trail can make a major difference if payment is later disputed.

Payment, Retention And Late Payment

A fixed fee doesn't mean a single payment at the end. Most construction subcontractors need progress payments so they can cover labour, materials and cash flow while the project is moving.

Your agreement should state the contract sum, whether VAT is included or added, when payment applications can be made, what information must be provided, and when payment is due. If the Construction Act applies, the contract should include a compliant payment mechanism, including due dates, final dates for payment, payment notices and pay less notices.

If retention applies, be clear about the percentage, when it's deducted, and when each part is released. For example, some contracts release part of the retention at practical completion and the balance after the defects period. If this isn't clearly written down, retention can become a long-running cash flow headache.

Late payment clauses should also be practical. You may want the right to charge interest, recover reasonable debt recovery costs, suspend work where the law allows, or stop ordering materials until overdue amounts are resolved. If you're the main contractor, you'll want a process that lets you raise genuine defects or set-off issues properly, rather than withholding payment informally.

Try to avoid vague terms such as "pay when paid". In many construction contracts, pay when paid clauses are restricted and may not be effective except in limited insolvency situations. Your subcontract should stand on its own payment timetable.

Delays, Site Access And Programme Risk

Fixed fee jobs often go wrong when the subcontractor prices on one programme, but the site operates on another. If you expected a clear run and instead have to make repeated visits, work around other trades or store materials off-site, your costs can increase quickly.

Your subcontract should deal with who is responsible for site readiness, access, storage, welfare facilities, parking, temporary power, scaffolding and information needed to do the work. These practical points can matter just as much as the legal clauses.

It should also explain what happens if you're delayed by something outside your control. You might need an extension of time, the right to claim additional costs, or at least protection from delay damages where the delay wasn't your fault.

If you're the contractor, you should make sure the subcontractor has clear notice obligations. For example, they may need to tell you promptly if access isn't available, drawings are missing or another trade is preventing progress. Early notice gives everyone a better chance of fixing the issue before it becomes expensive.

On fixed fee work, the best approach is to tie the price to clear assumptions. If those assumptions change, there should be a clear contractual path for dealing with the cost and time impact.

Defects, Insurance And Compliance

A strong subcontract doesn't stop at completion. It should also explain what happens if defects are identified, how long the defects period lasts, and how quickly the subcontractor must return to inspect or fix the issue.

Defects clauses should be balanced. The contractor needs a way to have defective work corrected. The subcontractor needs a fair chance to inspect the issue and confirm whether it was caused by their work, by others, by poor site conditions or by later damage.

Insurance is another key part of the risk picture. Depending on the works, the agreement may require public liability insurance, employer's liability insurance, contractor's all risks cover, professional indemnity insurance for design work, or product liability cover. The contract should state the required levels and whether certificates need to be provided before work starts.

Construction work also comes with health and safety obligations. Your subcontract may need to cover method statements, risk assessments, site rules, inductions, permits, CDM requirements, licences, qualifications and compliance with applicable laws and standards. If you're working in a regulated trade, make sure the agreement lines up with the certifications and sign-off the project needs.

Finally, think about documents at handover. You may need to provide warranties, manuals, test certificates, as-built information, maintenance instructions or guarantees. If these are required before final payment is released, the agreement should say so clearly.

Key Takeaways

  • A fixed fee is only fixed for the agreed scope, so the scope, assumptions and exclusions need to be clear.
  • Put the subcontract in writing, especially where there are drawings, staged payments, retention, site access issues or compliance requirements.
  • Use a clear variation process so extra work, changed drawings and delays caused by others can be priced and approved properly.
  • Make sure payment terms deal with applications, due dates, payment notices, pay less notices, retention and late payment rights.
  • Cover practical risks such as site readiness, programme changes, defects, insurance, health and safety and handover documents.

If you'd like help with fixed fee subcontractor agreements, scope of works clauses, payment terms or variation processes, you can reach us at 08081347754 or team@sprintlaw.co.uk for a free, no-obligations chat.

Lock in the contract

Turning the information into a usable contract

Once money, deliverables or customer obligations are involved, the next step is usually a clear contract that matches how the business actually works.

Alex Solo
Alex SoloCo-Founder

Alex is Sprintlaw’s co-founder and principal lawyer. Alex previously worked at a top-tier firm as a lawyer specialising in technology and media contracts, and founded a digital agency which he sold in 2015.

Lock in the contract

Get in touch with our team

Tell us what you need and we'll come back with a fixed-fee quote - no obligation, no surprises.

Need support?

Need help with your business legals?

Speak with Sprintlaw to get practical legal support and fixed-fee options tailored to your business.